The Turfgrass Sod Installation Process
Installing sod is a 4-step process that includes site preparation, soil preparation, sod installation and watering. Whether you live in Greensboro, Winston-Salem or surrounding areas of NC, by following these 4 simple installation steps, you can have a beautiful, green turf grass lawn.Preparing The Site For The Turfgrass Sod
Your lawn must be prepared before the sod is installed. This important step of site preparation must not be overlooked. Failure to properly prepare the site and soil could mean your sod does not properly take root in the soil. A well-prepared site and soil means your turf grass grow deep roots, which results in a healthy, greener lawn.Site preparation steps:
1. Clear the site of any rocks, wood, stumps, etc. 2. Ensure the area is properly sloped away from any foundations and low-lying areas are leveled for proper water drainage. 3. Till the site to eliminate the soil from being too compact. This step will make it easier for the sod to take root and improve water penetration. 4. Add quality topsoil to the site. 5. Test the pH of the soil to see if it is acidic or alkaline. Depending on your finding, lime or sulfur may need to be added. 6. Rake the area or use a lawn roller to level the site. This process ensures the site is level and settles the soil. 7. Your site is now prepared and you are ready for the next step, installing the sod.Turfgrass Sod Installation Steps
In the previous steps, we discussed how to prepare the site for the turfgrass sod, now let’s look at steps of the installation process. 1. Measure your lawn with a tape measure and draw a rough outline of the lawn with the measurements 2. Call or visit Southern Sodgrass and we will help you determine how much sod you need for your lawn. 3. Schedule a delivery time. It is important that the site preparation be complete so the sod can be laid the day of delivery. 4. Turfgrass sod should be laid along side the longest straight line, like a sidewalk. Edges of the sod should be laid tightly against each other and do not overlap the sod. Sod should be staggered like a brick pattern. Do not leave small pieces on the ends as they will dry out quickly. 5. Roll the sod to ensure that it contacts the soil and remove any air pockets that have formed. 6. Water the turfgrass sod within the first 20-30 minutes after installation. 7. Keep the sod wet for at least 2-3 weeks, but never over water.The Turfgrass Sod Installation Process
Installing sod is a 4-step process that includes site preparation, soil preparation, sod installation and watering. Whether you live in Greensboro, Winston-Salem or surrounding areas of NC, by following these 4 simple installation steps, you can have a beautiful, green turf grass lawn.
Preparing The Site For The Turfgrass Sod
Your lawn must be prepared before the sod is installed. This important step of site preparation must not be overlooked. Failure to properly prepare the site and soil could mean your sod does not properly take root in the soil. A well-prepared site and soil means your turf grass grow deep roots, which results in a healthy, greener lawn.
no-repeat;center top;;
auto
Site preparation steps:
1. Clear the site of any rocks, wood, stumps, etc.
2. Ensure the area is properly sloped away from any foundations and low-lying areas are leveled for proper water drainage.
3. Till the site to eliminate the soil from being too compact. This step will make it easier for the sod to take root and improve water penetration.
4. Add quality topsoil to the site.
5. Test the pH of the soil to see if it is acidic or alkaline. Depending on your finding, lime or sulfur may need to be added.
6. Rake the area or use a lawn roller to level the site. This process ensures the site is level and settles the soil.
7. Your site is now prepared and you are ready for the next step, installing the sod.
no-repeat;center top;;
auto
Turfgrass Sod Installation Steps
In the previous steps, we discussed how to prepare the site for the turfgrass sod, now let’s look at steps of the installation process.
1. Measure your lawn with a tape measure and draw a rough outline of the lawn with the measurements
2. Call or visit Southern Sodgrass and we will help you determine how much sod you need for your lawn.
3. Schedule a delivery time. It is important that the site preparation be complete so the sod can be laid the day of delivery.
4. Turfgrass sod should be laid along side the longest straight line, like a sidewalk. Edges of the sod should be laid tightly against each other and do not overlap the sod. Sod should be staggered like a brick pattern. Do not leave small pieces on the ends as they will dry out quickly.
5. Roll the sod to ensure that it contacts the soil and remove any air pockets that have formed.
6. Water the turfgrass sod within the first 20-30 minutes after installation.
7. Keep the sod wet for at least 2-3 weeks, but never over water.
no-repeat;center top;;
auto